Sprint capacity calculator

Add the people on the team and the days each of them is available. The calculator returns the capacity of the sprint in focus hours and person-days, and scales your velocity to match.

What sprint capacity means

Sprint capacity is the amount of working time the team really has in one sprint. It is not a fixed number. People take leave, public holidays fall inside the sprint, someone is on support duty, a new colleague joins halfway. Capacity planning counts that time before the team commits to work, so the plan reflects the sprint you are about to have and not an ideal one.

Velocity looks backward: it is the number of points the team finished in past sprints. Capacity looks forward: it is the time available in the next one. The two work together. Velocity tells you what a normal sprint delivers, and capacity tells you how far the next sprint is from normal.

How the calculator works

For each person the calculator multiplies three numbers.

  • Days available. The working days in the sprint, minus leave, holidays and days spent on other projects.
  • Hours a day. The length of the working day. Enter fewer hours for part-time colleagues.
  • Focus factor. The share of working time that goes to sprint work. The rest goes to meetings, email, reviews for other teams, support and interruptions.

The sum for the whole team is the capacity in focus hours. The sum of the days alone is the capacity in person-days.

The focus factor is a common practice, not a rule of Scrum. Many teams start from a value around 60 to 80 percent and correct it after a few sprints. The calculator starts at 70 percent. Use a lower value for people with many meetings or support duties, and a higher one for people who work on the sprint without interruptions. An honest low number is more useful than a flattering high one.

Worked example

A team of five plans a two-week sprint of 10 working days. Everyone works 8 hours a day with a focus factor of 70 percent.

  • Ana, Ben and Dev are available for all 10 days.
  • Chloe takes 3 days of leave, so she has 7 days.
  • Eli spends half of the sprint on another project, so he has 5 days.

The team has 10 + 10 + 10 + 7 + 5 = 42 person-days, out of 50 possible. That is 42 × 8 = 336 working hours. With a 70 percent focus factor, capacity is 336 × 0.7 = 235.2 focus hours.

The team's average velocity is 30 points, measured in sprints where all five people were present for all 10 days, which is 50 person-days. The adjusted velocity for this sprint is 30 × 42 ÷ 50 = 25.2 points. During sprint planning the team should plan for about 25 points and not 30.

Using the result in sprint planning

Teams that plan with story points use the adjusted velocity: it is a first guess at how many points to pull into the sprint. Teams that break stories into tasks estimated in hours compare the total of those tasks with the focus hours. Both are a sanity check, not a target. The team still decides what it can commit to.

Two cautions. First, capacity does not turn points into hours. Story points and hours measure different things, and a fixed exchange rate between them breaks relative estimation. Second, the adjustment assumes people are interchangeable, which they are not. If the only person who knows the payment system is away, a story in that area may not fit even when the numbers say it does.

The address of this page changes as you type and holds your numbers. Bookmark it or share it with the team to reopen the same calculation next sprint. Once you know how much fits, start a free session to estimate the stories with planning poker.

Frequently asked questions

How do you calculate sprint capacity?

For each team member multiply the days available in the sprint by the hours worked per day and by the focus factor, then add the results. The total is the team's capacity in focus hours. The sum of the days alone gives capacity in person-days.

What is a good focus factor?

There is no standard value. Many teams start between 60 and 80 percent and adjust after a few sprints by comparing what they planned with what they finished. People with many meetings or support duties need a lower value.

What is the difference between capacity and velocity?

Velocity is the number of story points the team completed in past sprints. Capacity is the working time available in the coming sprint. Capacity tells you whether the next sprint is likely to match the usual velocity.

How do I adjust velocity for holidays?

Multiply the average velocity by the person-days available this sprint and divide by the usual person-days. A team with a velocity of 30 points and 42 of its usual 50 person-days should plan for about 25 points.