Sprint planning meeting: agenda, attendees and how to run it

Sprint Planning starts every sprint. Here is who attends, a practical agenda you can reuse, and how to leave the room with a Sprint Goal and a plan the team believes in.

On this page
  1. Who attends sprint planning
  2. Before the meeting
  3. A sprint planning agenda for a two-week sprint
  4. The three topics: why, what and how
  5. A worked example
  6. Common mistakes
  7. Sprint planning checklist
  8. Frequently asked questions

A sprint planning meeting is the Scrum event that starts each sprint. The whole Scrum Team (Product Owner, Scrum Master and Developers) agrees on why the sprint is valuable, which Product Backlog items it can complete, and how the Developers will do that work. The output is the Sprint Backlog: a Sprint Goal, the selected items and a plan for delivering them.

The Scrum Guide calls this event Sprint Planning and timeboxes it to a maximum of eight hours for a one-month sprint, with shorter sprints usually needing less. This guide turns that definition into a meeting you can actually run.

Who attends sprint planning

RoleWhat they bring
Product OwnerThe ordered Product Backlog, the business objective for the sprint, answers about scope and priorities
DevelopersKnowledge of the work, their own capacity, the decision on how much they can take on
Scrum MasterFacilitation, timekeeping, making sure the event produces a goal and a plan
Invited experts (optional)Specific advice, for example a security specialist or another team that owns a dependency

The Developers decide how much work to select. The Product Owner can propose and explain, but cannot assign a fixed amount of work to the team.

Before the meeting

Most of what makes Sprint Planning short happens before it starts. Check three things the day before:

  • The top of the backlog is refined. The items likely to be selected have acceptance criteria and estimates. If they don't, the meeting becomes a refinement session. See backlog refinement.
  • Capacity is known. Holidays, part-time schedules, on-call duty and public holidays are collected. Sprint capacity planning explains how to turn them into a realistic number.
  • The last sprint is closed. The Sprint Review and Retrospective are done, and unfinished items are back on the Product Backlog for the Product Owner to reorder.

A sprint planning agenda for a two-week sprint

This agenda fits a team of five to eight people working in two-week sprints. Adjust the times to your context; the order matters more than the minutes.

  1. Opening (5 minutes). The Scrum Master states the timebox and the expected outputs: Sprint Goal, selected items, a plan for the first days.
  2. Context (10 minutes). The Product Owner shares what was learned in the Sprint Review and what matters most now.
  3. Capacity (10 minutes). The team confirms availability and looks at its recent velocity range.
  4. Draft Sprint Goal (15 minutes). The Product Owner proposes an objective; the team discusses and refines it.
  5. Select items (30 to 45 minutes). The Developers pull items from the top of the backlog that serve the goal, until the total fits their capacity.
  6. Plan the work (30 to 45 minutes). The Developers break the first items into tasks or steps and agree who starts where.
  7. Confirm (5 minutes). Read the Sprint Goal aloud and check everyone can commit to it.

If you want this as a ready-made document, the sprint planning agenda template has the same steps with space for notes.

For a one-week sprint, halve the selection and planning blocks. For a four-week sprint, plan the first week in detail and leave the rest at the level of items, since the plan will change as the team learns.

The three topics: why, what and how

Why is this sprint valuable?

The Sprint Goal is a single objective for the sprint, written so that anyone can tell at the end whether it was met. "Customers can pay with a saved card" is a goal. "Finish tickets 412, 415 and 419" is a list. The goal gives the team room to adjust scope during the sprint while still delivering what matters.

What can be done this sprint?

The Developers select items that serve the goal. Velocity and capacity set the limit together. If the team's last three sprints delivered 22, 26 and 24 points and one of six people is away for half the sprint, the team has about eleven twelfths of its usual availability, so planning around 22 points is more honest than planning around 26.

How will the chosen work get done?

The Developers decide how to turn the items into a working increment. Some teams break each item into tasks of a day or less; others only plan the first few days in detail and refine the rest as they go. Both are fine. The plan belongs to the Developers.

A worked example

A team of six runs two-week sprints. Recent velocity: 24, 21 and 27 points. One developer is on holiday for five of the ten days, so the team has 55 of its usual 60 person-days. The average of 24 points scaled by 55 / 60 gives 22, and the team plans for about 20 to leave some slack.

The Product Owner proposes the goal: "Customers can save a card and use it at checkout." The top of the backlog contains:

  • Save a card during checkout: 8 points
  • Pay with a saved card: 5 points
  • Delete a saved card from the account page: 3 points
  • Show the card brand icon in the card list: 2 points
  • Redesign the order confirmation email: 5 points

The first four items serve the goal and total 18 points. The email redesign does not serve the goal, and adding it would bring the total to 23, above the planned 20. The team leaves it on the backlog. Two stories near the top have no estimate yet, so the team sizes them in a quick round of planning poker and confirms they belong to a later sprint.

In the last part of the meeting the Developers split "Save a card during checkout" into tasks for the first three days and agree that two people will pair on the payment provider changes.

Common mistakes

  • Refining during planning. Writing acceptance criteria and estimating from scratch in the meeting doubles its length. Keep refinement as an ongoing activity before planning.
  • Filling to 100 percent. Planning to the top of the velocity range leaves no room for bugs, support or surprises.
  • A goal that is a list of tickets. Without a real objective, the team cannot make trade-offs during the sprint.
  • The Product Owner deciding the amount. The Developers select how much work they can do. Pressure to take more usually ends in carry-over.
  • No plan for the first days. Leaving without knowing who starts what wastes the first morning of the sprint.

Sprint planning checklist

  • Top backlog items are refined and estimated before the meeting.
  • Capacity is collected, including holidays and on-call duty.
  • The Sprint Goal is one sentence and testable at the end of the sprint.
  • Selected items fit within the recent velocity range, adjusted for capacity.
  • The first items are broken down enough to start the next morning.
  • The Sprint Backlog is visible to the whole team.

Frequently asked questions

Who attends the sprint planning meeting?

The whole Scrum Team: the Product Owner, the Scrum Master and the Developers. The team can invite other people to give advice on specific topics.

How long should sprint planning take?

The Scrum Guide sets a maximum of eight hours for a one-month sprint. Shorter sprints usually need less time, and a well-refined backlog keeps the meeting short.

What is the output of sprint planning?

The Sprint Backlog: a Sprint Goal, the Product Backlog items selected for the sprint, and a plan for delivering them.

Who decides how much work goes into the sprint?

The Developers. The Product Owner explains priorities and proposes the objective, but the Developers select how much work they can complete.

Should stories be estimated during sprint planning?

Ideally most estimation happens earlier, during backlog refinement. Sprint Planning can handle a few unestimated items quickly, but it should not become a refinement session.