Burnup chart

A burnup chart is a graph with two lines over time: the total scope of the work and the amount completed so far. Delivery is forecast where the two lines meet.

Where a burndown shows only what remains, a burnup separates two things: how much has been done and how big the whole job is. The completed line rises as items are finished. The scope line moves up when work is added and down when work is removed. That makes burnups especially useful for releases, where scope almost always changes.

Example

A release starts with 200 points of scope. After four sprints the team has completed 150 points, at about 38 per sprint. Meanwhile the scope line has risen to 260 because the Product Owner added two features. A burndown would show 110 points left and look slow. The burnup shows clearly that the team kept its pace and the target moved. At 38 points per sprint, the lines should meet in about three more sprints.

Common misunderstanding

Burnups and burndowns are not competing tools; they answer different questions. A sprint burndown is fine for a two-week view with stable scope. A release burnup is better when stakeholders want to know why the date moved, because it shows whether progress slowed or scope grew.

Why it matters for estimation

Projecting the completed line with a range of velocities, rather than one number, gives an honest forecast range. The sprint velocity guide and the velocity forecast calculator show how.