Sprint planning agenda template

A two-hour agenda for planning a two-week sprint, with timings and an owner for every step. Copy it as text or Markdown and paste it into your meeting invite.

Sprint planning agenda

Before the meeting Product owner and Scrum master

  • The top of the backlog is ordered and refined, with more ready stories than one sprint can hold
  • A draft sprint goal is written down
  • Leave, holidays and other absences in the sprint are known
  • The velocity of the last few sprints is at hand

1. Open and confirm capacity 10 min, Scrum master

  • State the sprint dates and the purpose of the meeting
  • Confirm who is available and for how many days
  • Recall the recent velocity and adjust it for this sprint's capacity
  • List any unfinished work carried over from the last sprint

2. Why: the sprint goal 15 min, Product owner

  • Present the draft goal and why it matters now
  • Show the backlog items that serve the goal
  • Take questions from the team

3. What: select the work 45 min, whole team

  • Walk through the candidate stories in backlog order
  • Confirm the acceptance criteria of each story
  • Estimate any story that has no estimate yet, with planning poker
  • Stop adding stories when the total reaches the adjusted velocity

4. How: plan the first days 35 min, Developers

  • Break the first stories into tasks
  • Name dependencies, risks and anything that needs another team
  • Agree who starts on what

5. Confirm and close 15 min, whole team

  • Write the final wording of the sprint goal
  • Ask each person whether the plan is realistic, and adjust if someone doubts it
  • Record the sprint backlog where everyone can see it
  • Note open questions with an owner for each

How the agenda is built

Sprint planning answers three questions, in this order: why is this sprint valuable, what can be done in it, and how will the work get done. The agenda follows the same order. The first block sets the limits, the second gives the sprint a goal, the third selects the work, the fourth turns the first stories into a plan, and the last one checks that everyone believes it. The guide to the sprint planning meeting explains each part in depth.

The preparation section matters as much as the meeting. Planning runs long when stories arrive unrefined, because the team has to do backlog refinement and planning at once. If the top of the backlog already meets your definition of ready, block 3 is mostly a confirmation.

Timings and roles

The template takes 120 minutes and is sized for a two-week sprint. The Scrum Guide sets a maximum of eight hours for a one-month sprint and says shorter sprints usually need less. Many teams with two-week sprints finish in two hours or less once the backlog is in good shape.

  • Product owner: brings the ordered backlog and the draft goal, and answers questions about scope.
  • Developers: decide how much they can take on and how to do it. Nobody else sets that number for them.
  • Scrum master: keeps the time, makes sure capacity is on the table, and watches that the quieter voices are heard.

How to adapt it

  • One-week sprint. Halve every block. Keep the goal and the final check, even if each takes five minutes.
  • Longer sprint. Add time to blocks 3 and 4, not to the opening.
  • Stories already estimated. Shorten block 3 and spend the time on block 4.
  • Remote team. Add a five-minute break after block 3, and share the agenda in the chat so people can follow the timings.

Two numbers make block 1 quick. The sprint capacity calculator turns absences into an adjusted velocity, and the velocity forecast calculator shows how the sprint fits the release. For block 3, start a free session, paste the candidate stories one per line, and estimate the ones that still need a number. Votes stay secret until the reveal, and nobody has to sign up.

Frequently asked questions

How long should sprint planning take?

The Scrum Guide sets a maximum of eight hours for a one-month sprint, and shorter sprints usually need less. For a two-week sprint, two hours is a reasonable plan when the backlog has been refined beforehand.

Who attends sprint planning?

The whole Scrum team: the developers, the product owner and the Scrum master. The team can invite other people to give advice on specific items.

What is the output of sprint planning?

A sprint goal, the backlog items selected for the sprint, and a plan for delivering them. Together these form the sprint backlog.