The Fibonacci planning poker deck

Ten cards: 0, 1, 2, 3, 5, 8, 13, 21, 34 and a question mark. A common choice for teams that estimate in story points.

  • 0
  • 1
  • 2
  • 3
  • 5
  • 8
  • 13
  • 21
  • 34
  • ?

The Fibonacci deck as it appears in a Scrum Poker session. A coffee card is optional.

The values and what they mean

After 1 and 2, each number in the sequence is the sum of the two before it, so the gaps between cards grow as the numbers grow. That is the point of the deck. A small story can be told apart from a slightly bigger one, but nobody can honestly tell a 20 from a 21, so the deck does not offer the choice. The guide to Fibonacci estimation covers the reasoning in full.

  • 0: already done, or so small that it is not worth tracking.
  • 1, 2, 3: small, well understood work. Most teams anchor on a familiar story at 1 or 2 and compare everything else to it.
  • 5 and 8: medium stories with several parts or some unknowns. Still comfortable inside one sprint.
  • 13: large. It may fit in a sprint, but it deserves a conversation about splitting.
  • 21 and 34: too big to plan with confidence. Treat these cards as a signal to split the story, not as a real estimate.
  • ?: "I do not know enough to estimate." The story needs more discussion before a second vote.

The numbers are story points: relative sizes, not hours or days. A 5 is a bit more than twice the team's 2, and that is all it says.

When this deck fits

Choose the Fibonacci deck when the team estimates user stories in story points during refinement or sprint planning. It suits teams that have a reference story everyone remembers and that want enough small values (1, 2, 3, 5) to tell everyday stories apart.

It fits less well in two cases. When you size large items such as epics for a roadmap, the numbers suggest more precision than you have, and T-shirt sizes are a better match. When the team keeps arguing whether the top cards should be 21 or 20, the modified Fibonacci deck with its rounded 20, 40 and 100 ends that debate.

Worked example

The team's reference is "Add a sort option to the orders table", agreed at 2. The next story is "Export orders to CSV".

Everyone picks a card in private and the cards are revealed together: 3, 3, 5, 5 and 13. The spread between 3 and 13 is the useful part. The person who played 13 explains that the export must cover orders with refunds, which live in another service. The person who played 3 had assumed only the visible columns.

The product owner confirms that refunds can wait. The team votes again and lands on 5, 5, 5, 5 and 3. They agree on 5 and write the refund case down as a separate story. Two rounds, a few minutes, and a hidden assumption found before any code was written.

Use this deck

You can start a session with the Fibonacci deck for free, without signing up. For a co-located team, the printable cards give you the same values on paper. The planning poker cards guide compares all the common decks.

Frequently asked questions

What are the values in a Fibonacci planning poker deck?

The deck in Scrum Poker has 0, 1, 2, 3, 5, 8, 13, 21 and 34, plus a question mark card for when someone cannot estimate. A coffee card for breaks is optional.

Why is there no 4 or 6 in the deck?

Because the gaps are deliberate. As work gets bigger, estimates get less precise, so the deck only offers values that are clearly different from each other. Choosing between 3 and 5 is a real decision. Choosing between 5 and 6 is noise.

What should we do when someone plays 21 or 34?

Treat it as a sign that the story is too big or too unclear to plan. Ask what makes it large, then split it into smaller stories and estimate those.