A sprint burndown usually starts at the total estimate of the sprint backlog when the sprint begins and should reach zero by the end of the last day. A straight "ideal" line from start to finish is often drawn for comparison. The actual line goes down as items are finished. A release burndown works the same way, with sprints on the horizontal axis and the remaining release backlog on the vertical one. Burndown charts are a common practice, not a Scrum Guide requirement.
Example
A team starts a 10 day sprint with 32 points. By day 5 the line is at 24, well above the ideal line at 16, because two large stories are in progress but not done. On day 7 both finish and the line drops to 11. On day 10 one 3 point story is still open, so the sprint ends at 3.
Common misunderstanding
A burndown that follows the ideal line exactly is not a sign of a healthy sprint; it is often a sign that people are reporting progress to match the line. Burndowns also hide scope changes: if work is added and finished in the same week, the line looks flat. A burnup chart shows scope separately.
Why it matters for estimation
Burndowns only move when items are done, so large stories create long flat stretches followed by cliffs. Smaller stories give a smoother, more honest line. See user story splitting and sprint velocity.