The Daily Scrum is for the Developers. It is held at the same time and place every working day to reduce complexity. The 2020 Scrum Guide does not prescribe a format: the old three questions (what did I do yesterday, what will I do today, what is blocking me) are one option among many. The Product Owner and Scrum Master take part as Developers only if they are actively working on sprint backlog items.
Example
On day 6 of a sprint, the team walks its board from right to left. The payment story has been in review for two days. One Developer offers to review it straight after the meeting. Another mentions the declined-card story turned out bigger than expected; the team agrees to discuss it with the Product Owner that afternoon rather than in the Daily Scrum itself.
Common misunderstanding
The Daily Scrum is not a status report to a manager, and it is not the only time the team is allowed to talk. Detailed problem solving should happen afterwards, with the people who need to be there, so the event stays within 15 minutes.
Why it matters for estimation
The Daily Scrum is not a place to re-estimate stories. If a story turns out much larger than expected, note it, and discuss scope with the Product Owner. See estimation anti-patterns and sprint planning.