Definition of ready checklist

Twelve checks a user story should pass before it enters a sprint. Copy the checklist as text or Markdown, then cut it down to what your team needs.

Definition of ready checklist

The story is clear

  • It says who needs it, what they need and why
  • The team has discussed it and has no open questions that block the start
  • Designs, texts or data needed to build it are attached

It can be tested

  • Acceptance criteria are written and agreed with the product owner
  • The team knows how it will show that the story works

It is small enough

  • The team has estimated it
  • It fits comfortably within one sprint
  • A story that is too large has been split

It can start

  • Dependencies on other teams, systems or decisions are known and resolved or scheduled
  • No work outside the team has to finish first, or it has a date

It is worth doing now

  • The product owner has placed it in backlog order
  • It contributes to a goal the team understands

What "ready" means

A definition of ready is a short list of conditions a backlog item should meet before the team takes it into a sprint. It protects the sprint from stories that look simple in planning and fall apart on day two because nobody knew what "done" meant or another team had to deliver first.

The definition of ready is a team agreement, not an official part of Scrum. The Scrum Guide only says that items which can be done within one sprint are considered ready for selection in sprint planning. Everything beyond that is a practice teams add because it helps them.

How to use the checklist

Use it during backlog refinement, not as a form to fill in afterwards. When the team finishes discussing a story, run down the list. Most checks take a second. The one that fails tells you what to do next: write the missing acceptance criterion, split the story, or ask the other team for a date.

The check "the team has estimated it" does more work than it seems. An estimate from planning poker shows whether the story is understood: close votes mean shared understanding, a wide spread means the story is not ready, whatever the other boxes say. An estimate also shows whether the story fits in a sprint or needs splitting.

Who owns it

  • Product owner: makes sure stories arrive at refinement with a clear need and draft acceptance criteria.
  • Developers: judge whether a story is clear, testable and small enough. They are the ones who will build it.
  • Scrum master: helps the team write the definition, keep it short and revisit it in retrospectives.

How to adapt it

  • Keep it short. Five to eight checks that the team really applies beat a long list nobody reads. Delete lines that never fail for you.
  • Add what bites you. If stories often stall on missing translations, test data or security review, add a line for it.
  • Do not make it a gate. The checklist is a guide for a conversation. If a story misses one check and the team is confident, take it and note the risk. A rigid gate turns refinement into paperwork and slows the team down.
  • Review it. When a story fails in the sprint for a reason the checklist could have caught, update the checklist.

To cover the estimation check, start a free session and paste the stories you are refining, one per line. The team votes in secret, reveals together and saves an agreed estimate on each story. Nobody needs an account.

Frequently asked questions

What is a definition of ready?

It is a team's shared list of conditions a backlog item should meet before it is taken into a sprint, such as being clear, testable, estimated and small enough to finish within the sprint.

Is the definition of ready part of Scrum?

No. The Scrum Guide defines a definition of done but not a definition of ready. It is a common complementary practice that many teams adopt to make sprint planning smoother.

What is the difference between definition of ready and definition of done?

The definition of ready describes when a story can enter a sprint. The definition of done describes when work is complete and of the required quality. Ready is a team convention, done is a formal commitment in Scrum.