Your numbers
Forecast
- Average velocity
- Lowest to highest
- Best 3 average
- Worst 3 average
| Scenario | Sprints needed | Last sprint ends |
|---|---|---|
| Optimistic | ||
| Likely | ||
| Pessimistic |
Enter the remaining backlog in points to see how many sprints it needs.
Sprints needed = remaining points ÷ velocity, rounded up. Optimistic uses the average of the 3 best sprints, likely uses the average of all sprints, pessimistic uses the average of the 3 worst. Last sprint ends = first day + sprints × sprint length, minus one day, moved back to Friday when it falls on a weekend.
Why forecast with a range
A single date invites a promise. "We will be done on 12 March" sounds precise, but velocity changes from sprint to sprint, and a date built on one average hides that. A range is more honest and more useful: it shows what happens if the coming sprints look like your best ones, your typical ones, or your worst ones.
This calculator uses a simple method that many teams apply by hand. It is a common practice, not an official part of Scrum, and it needs nothing more than the numbers you already have.
The method
- Collect recent velocities. Take the points completed in each of the last 3 to 10 sprints. Older sprints say little about the team you have today.
- Compute three velocities. The average of the 3 best sprints is the optimistic velocity. The average of all sprints is the likely velocity. The average of the 3 worst sprints is the pessimistic velocity.
- Divide the backlog. Divide the remaining points by each velocity and round up, because a partly used sprint is still a sprint.
- Turn sprints into dates. Multiply the number of sprints by the sprint length and count from the first day of the next sprint. The day before that is the last day of the final sprint.
With only three sprints entered, the best three and the worst three are the same sprints, so the three scenarios give the same answer. The range starts to say something from five or six sprints.
Worked example
A team finished 21, 25, 19, 23, 27 and 22 points in its last six sprints. The backlog for the release holds 150 points. Sprints are two weeks long.
- Average: 137 points over 6 sprints is 22.8 points per sprint.
- Best 3: 27, 25 and 23 average 25 points per sprint.
- Worst 3: 19, 21 and 22 average 20.7 points per sprint.
Now divide the backlog. 150 ÷ 25 = 6 sprints in the optimistic case. 150 ÷ 22.8 = 6.6, rounded up to 7 sprints in the likely case. 150 ÷ 20.7 = 7.3, rounded up to 8 sprints in the pessimistic case.
If the next sprint starts on Monday 7 December 2026, the optimistic forecast ends on Friday 26 February 2027, the likely one on 12 March and the pessimistic one on 26 March. The honest answer to "when will it be done?" is "most likely in mid March, and between late February and late March".
How to read and share the forecast
Share the range, not only the middle. Stakeholders can plan around "between 6 and 8 sprints" far better than around a date that later slips. Update the forecast after every sprint: the remaining backlog shrinks, the newest velocity replaces the oldest, and the range usually narrows as the release gets closer.
The forecast is only as good as its inputs.
- The backlog must be estimated. Stories without an estimate are invisible to the forecast. Size them in backlog refinement, even roughly, before trusting the dates.
- Scope changes move the dates. If stories are added, raise the remaining points. A backlog that grows as fast as the team delivers never finishes.
- Velocity belongs to one team. Points are relative to each team's own baseline, so never compare or add velocities across teams. The sprint velocity guide explains why.
- Unusual sprints distort the picture. A sprint with half the team on holiday pulls the pessimistic case down. Check next sprint's availability with the sprint capacity calculator.
The address of this page holds your numbers, so you can bookmark the forecast or send it to a colleague. To put estimates on the remaining stories, start a free session and size them with planning poker.
Frequently asked questions
How do I forecast a release date from velocity?
Divide the remaining story points by the team's velocity and round up to get the number of sprints, then multiply by the sprint length. Do it three times, with the best, average and worst recent velocity, to get a range and not a single date.
How many sprints should I use to calculate average velocity?
Use the most recent 3 to 10 sprints. Fewer than three is too little to see a pattern, and sprints from long ago describe a team and a product that may have changed.
Why does the calculator give a range and not one date?
Velocity varies from sprint to sprint, so one date would hide real uncertainty. The optimistic, likely and pessimistic cases show how far the finish can move if coming sprints look like your best, typical or worst ones.
Is this forecast method part of Scrum?
No. Scrum does not prescribe a forecasting method. Using the average of the best and worst three sprints is a common, simple practice that teams apply on top of their velocity data.