Scrum Poker Starta session

Sprint capacity planning: availability, focus factor and velocity

Sprint capacity planning tells you how much work your team can realistically take on in the next sprint, given who is available and for how long. This guide shows how to calculate it, step by step, with real numbers.

On this page
  1. Capacity vs velocity
  2. Step 1: calculate availability
  3. Step 2: apply a focus factor
  4. A worked example with numbers
  5. Using capacity in sprint planning
  6. Common mistakes
  7. Capacity planning for a new team
  8. Frequently asked questions

Sprint capacity planning is the practice of working out how much time a team actually has available in the coming sprint, after holidays, part-time schedules, Scrum events and other commitments, and using that figure to decide how much work to select. Capacity is measured in person-days or hours of available time. Combined with the team's velocity, it lets you adjust the plan when the sprint is shorter or the team is smaller than usual.

Capacity planning does not replace velocity. It explains why one sprint should hold less work than the last one, before the sprint starts rather than after it fails.

Capacity vs velocity

The two terms are often mixed up, but they measure different things.

AspectCapacityVelocity
What it measuresTime the team has availableWork the team completed
UnitPerson-days or hoursStory points per sprint
Looks atThe coming sprintPast sprints
Changes withHolidays, part-time work, team changesEverything, including capacity

Velocity tells you how many points the team usually finishes. Capacity tells you whether this sprint is usual. When capacity drops, you scale the velocity-based plan down to match. The sprint velocity guide covers how to measure velocity reliably.

Step 1: calculate availability

Start with the number of working days in the sprint, multiplied by the number of people who do the work. Then subtract known absences.

  • Public holidays that fall in the sprint.
  • Planned leave and training days.
  • Part-time schedules, for example someone who works four days a week.
  • Time someone spends on another team or project.

Count the Developers only: the people who build and test the work. The Product Owner and Scrum Master are usually left out unless they also pick up backlog items.

Step 2: apply a focus factor

Nobody spends a full working day on sprint work. Scrum events, support requests, code reviews for other teams, email and small interruptions all take time. The focus factor is the share of available time that actually goes into sprint backlog items.

There is no standard value. Many teams start with something between 0.6 and 0.8 and adjust it after a few sprints by comparing planned and actual work. A team with on-call duty or a heavy support load will have a lower focus factor than a team that is fully protected.

Do not use the focus factor to measure how hard people work. It describes how the team's environment uses its time. A low focus factor is a signal to look at interruptions, not at individuals.

A worked example with numbers

A team of five Developers works in two-week sprints, which is 10 working days. In a normal sprint the team has 5 × 10 = 50 person-days available. Over the last four normal sprints, the team completed 38, 42, 40 and 40 points, an average of 40 points.

The coming sprint is different:

  • A public holiday on one day: 5 people × 1 day = 5 person-days lost.
  • Priya is on leave for 3 days.
  • Marco spends 2 days supporting another team's release.
  • Lena has a 1 day training course.
ItemPerson-days
Normal availability (5 × 10)50
Public holidayminus 5
Priya's leaveminus 3
Marco supporting another teamminus 2
Lena's trainingminus 1
Available this sprint39

The simplest way to use this is a ratio. The team usually completes 40 points with 50 person-days. This sprint it has 39 person-days, so the expected velocity is 40 × 39 / 50 = 31.2 points. The team plans for about 31 points, not 40.

Compare like with like. If someone always works four days a week, their normal availability is 8 days, not 10, and it belongs in the baseline as well as in the current sprint. Only the differences from a normal sprint should change the plan.

Velocity varies from sprint to sprint, so it is often more honest to work with a range. Using the lowest and highest of the last four sprints (38 and 42), the adjusted range is 38 × 39 / 50 = 29.6 to 42 × 39 / 50 = 32.8, so roughly 30 to 33 points. Either way, planning 40 points would almost certainly overload the sprint.

Where the focus factor comes in

Teams that plan in hours apply the focus factor directly. With 39 person-days of 8 hours and a focus factor of 0.7, the team has 39 × 8 × 0.7 = about 218 hours for sprint work. Teams that plan in story points usually do not need the focus factor at all, because the ratio method already assumes the same mix of meetings and interruptions as in past sprints. If you want to skip the arithmetic, the sprint capacity calculator does it for you.

Using capacity in sprint planning

  1. Before the meeting, collect absences and calculate available person-days.
  2. At the start of sprint planning, share the number and the adjusted velocity, for example "about 31 points this sprint".
  3. Agree the Sprint Goal first, then select backlog items that support it until the total is close to the adjusted figure.
  4. Leave some slack. Many teams stop a little below the number to absorb surprises.
  5. Check after the sprint how close the plan was and adjust the focus factor or the baseline.

If your selected stories do not have estimates yet, estimate them in refinement before planning, not during it. A sprint planning agenda helps keep the meeting focused.

Common mistakes

  • Planning at full availability. Assuming every person works eight focused hours a day leads to overloaded sprints.
  • Ignoring known absences. A sprint with two holidays and a conference should not hold the same work as a normal one.
  • Assigning capacity per person. Filling each person's hours individually encourages silos. Plan capacity at team level.
  • Converting points to hours. Capacity is in time, velocity is in points. Use the ratio between normal and current availability, not a fixed hours-per-point rate.
  • Treating capacity as a target. Capacity is an upper bound for planning. Using all of it leaves no room for the unexpected.

Capacity planning for a new team

A new team has no velocity yet. In the first two or three sprints, plan in hours or person-days with a conservative focus factor such as 0.6, select work that seems to fit, and record how many points were completed. After three sprints you have a first velocity range, and you can switch to the ratio method described above. Expect the first few sprints to miss in both directions. That is normal, and it is the data the team needs to plan better.

Frequently asked questions

What is sprint capacity?

Sprint capacity is the amount of time a team has available for sprint work in a given sprint, usually measured in person-days or hours, after holidays, leave, part-time schedules and other commitments are removed.

What is the difference between capacity and velocity?

Capacity is the time the team has available in the coming sprint. Velocity is the amount of work, usually in story points, the team completed in past sprints. Capacity is used to adjust velocity when a sprint is unusual.

What is a focus factor?

A focus factor is the share of available time that goes into sprint backlog items, after meetings, support and interruptions. Teams often start between 0.6 and 0.8 and adjust it from experience.

How do you adjust velocity for a short sprint?

Multiply average velocity by the ratio of available person-days this sprint to available person-days in a normal sprint. For example, 40 points × 39 / 50 gives about 31 points.