The powers of 2 deck as it appears in a Scrum Poker session.
The values and what they mean
The scale is as simple as a scale can be: each step doubles. To move a story one card up, a team member has to believe it is about twice as much work. That makes the cards easy to explain and the debates short.
- 0: nothing to do, or too small to count.
- 1 and 2: small, familiar work. Pick a reference story for 1 or 2 and compare against it.
- 4 and 8: medium to large stories. An 8 is eight times a 1, which for many teams is near the limit of what fits in a sprint.
- 16: very large. Look for a way to split it.
- 32 and 64: epics. The card records a rough size and a need to break the item down.
- ?: not enough information to estimate.
Like other planning poker scales, the numbers are relative sizes, not hours.
Compared with Fibonacci
Both decks have gaps that grow with size, for the same reason: big work is uncertain work. The difference is in the low and middle range. Fibonacci offers 1, 2, 3, 5, 8, 13 where powers of 2 offers 1, 2, 4, 8, 16. There is no 3 and no 5, so a story that feels "between 2 and 4" must go one way or the other. Some teams like that, because it forces a decision. Others miss the finer steps for everyday stories.
When this deck fits
Choose powers of 2 when the team thinks naturally in doublings, which is common among engineers, or when estimation debates drag on over neighbouring values. With fewer cards in the sprint-sized range, agreement tends to come faster. The deck also suits teams whose work varies a lot in size, because 64 is only six doublings away from 1.
It fits less well when most of your stories are small and similar. If nearly everything is a 2 or a 4, the scale cannot show the differences that matter for planning, and a Fibonacci deck gives more resolution. It can also confuse people who read 8 and 16 as hours. If that happens, restate the reference story or switch to T-shirt sizes.
Worked example
The reference story is "Add a field to the customer profile form", agreed at 1. The team estimates "Let customers upload a profile picture".
The cards are revealed together: 4, 4, 8, 4 and 2. The person who played 8 is thinking about resizing images and storing them, and asks whether the storage service is set up. It is, since the last release. The person who played 2 had forgotten that the upload must also work in the mobile layout.
The facilitator asks the doubling question: "Is this twice the work of a 2, like the address form from last sprint?" Most say yes. "Is it twice that again?" Most say no. The team agrees on 4 and moves to the next story.
Use this deck
Start a session with the powers of 2 deck: free, no sign-up, and votes stay secret until everyone has played. You can print the same deck with the printable cards tool, and the planning poker cards guide compares all the decks side by side.
Frequently asked questions
What is the powers of 2 scale in planning poker?
It is a deck with the values 0, 1, 2, 4, 8, 16, 32 and 64, where every card is double the previous one. Scrum Poker adds a question mark card for stories that cannot be estimated yet.
Is powers of 2 better than Fibonacci for story points?
Neither is better in general. Powers of 2 has fewer values in the sprint-sized range, which makes voting quick but less fine-grained. Fibonacci gives more choices between 1 and 13. Pick one and stay with it so that velocity remains comparable.
Can we switch from Fibonacci to powers of 2?
Yes, but past velocity will not compare cleanly with new sprints, because stories that were 3 or 5 now become 2, 4 or 8. Re-estimate the reference stories on the new scale and give velocity a few sprints to settle.