Velocity

Velocity is the amount of work a team completes in a sprint, usually measured as the sum of story points of the backlog items that met the definition of done.

Velocity is measured after the fact. At the end of each sprint the team adds up the estimates of the items that are fully done. Partly finished work counts for nothing. Over several sprints, velocity gives a range that the team can use to forecast how much work fits in a future sprint or how many sprints a set of features might take. Velocity is not part of the Scrum Guide; it is a common practice that goes together with story points.

Example

A team completes 34, 41, 38 and 39 points in four sprints. Its velocity range is roughly 34 to 41, with an average of 38. With 190 points left in the release backlog, the team forecasts about five sprints, and says it could be five or six.

Common misunderstanding

Velocity is a planning tool for one team, not a productivity score. Comparing velocity between teams is meaningless because each team's points have a different size. Using velocity as a target usually leads to estimate inflation: the same work gets larger numbers, velocity rises and nothing else changes.

Why it matters for estimation

Velocity is what turns relative estimates into forecasts. It absorbs systematic errors, so if every story is a little harder than it looked, velocity drops and the forecast corrects itself. See the sprint velocity guide for how to measure it, and sprint capacity planning for adjusting it when a sprint has fewer working days.