How many story points per sprint should your team plan?

There is no right number of story points per sprint. There is a right number for your team this sprint, and you can work it out from recent velocity and the people available.

On this page
  1. Why there is no standard number
  2. Start from velocity
  3. Adjust for capacity
  4. A worked example
  5. Choosing the final number
  6. Forecasting beyond one sprint
  7. Common mistakes
  8. Frequently asked questions

How many story points per sprint has no universal answer, because story points are a relative unit that each team defines for itself. The number your team should plan is its recent average velocity, adjusted for the capacity it actually has this sprint. A team of six that usually finishes 20 to 26 points and has one person on holiday for half the sprint has about eleven twelfths of its usual availability, so it should plan around 21, not 30.

A figure like "a two-week sprint should hold 40 points" means nothing outside the team that produced it. One team's 5 can be another team's 13. What does carry over between teams is the method: measure what you finish, adjust for who is around, and plan a little below the result. This guide walks through that method with numbers.

Why there is no standard number

A story point has no fixed size. Each team anchors its scale on its own reference stories, as described in story points explained. If a team decides its smallest common task is a 1, and another team calls the same kind of task a 3, the second team's sprint totals will be about three times larger with no difference in output.

Team size, sprint length, the mix of work and the amount of unplanned work also change the total. A team of eight on three-week sprints will finish more points than a team of four on one-week sprints, even if both use the same scale. Comparing totals between teams tells you almost nothing about which team delivers more value.

Points per person is no better. Dividing velocity by headcount produces a number that people start to defend, and once that happens estimates inflate. Treat velocity as a property of the team, never of individuals.

Start from velocity

Velocity is the number of story points a team completes in a sprint, counting only items that meet the Definition of Done. Half-finished stories count zero. It is the best predictor you have, because it already includes meetings, reviews, support work and every other interruption the team had.

Use the last three to five sprints. One sprint is too noisy; ten sprints may include a different team or a different product. Take both the average and the range, because the range tells you how much to trust the average.

For example, a team with these recent results:

  • Sprint 14: 23 points
  • Sprint 15: 19 points
  • Sprint 16: 27 points
  • Sprint 17: 24 points

has an average of about 23 and a range of 19 to 27. A plan of 23 points is realistic; a plan of 30 is a wish.

If your team regularly handles unplanned work, such as production support or urgent requests, velocity already reflects the share of time it usually takes. When you know that share will change, for example because the team is on call for a launch, lower the plan to match. Change sprint length rarely, since every change resets the history you rely on and makes the old numbers hard to compare.

A new team without history can plan its first sprint by selecting stories it believes it can finish, then measure. After three sprints you will have a usable velocity.

Adjust for capacity

Velocity assumes a normal sprint. When the next sprint is not normal, scale it. The simplest method compares available person-days with the person-days in the sprints behind your velocity.

Count working days for each Developer in the sprint, subtract holidays, public holidays, training and any planned time on other work, then add them up. Do the same for a typical recent sprint. The ratio between the two gives you an adjustment factor. The sprint capacity planning guide covers the details, and the sprint capacity calculator does the arithmetic.

Keep the adjustment rough. You are correcting for large, known changes such as a public holiday or a person leaving, not trying to predict output to the point.

A worked example

A team of six Developers runs two-week sprints of 10 working days. In a normal sprint, everyone is present, so the team has 60 person-days. Its last four sprints finished 23, 19, 27 and 24 points: an average of about 23.

The next sprint looks different:

DeveloperDays availableReason
Ana10Full sprint
Ben5Holiday in week two
Chen9Public holiday
Dara9Public holiday
Eli8Public holiday and one day of training
Femi9Public holiday
Total50

The team has 50 of its usual 60 person-days, about 83%. Applying that to the average gives 23 × 0.83, roughly 19 points. Applying it to the range gives about 16 to 22.

At Sprint Planning the team pulls stories toward a Sprint Goal and stops around 19 points: a 5, two 3s, an 8. It keeps a 2 point story ready as a stretch item but does not count it in the forecast. If the sprint goes well, the team pulls the 2 in; if not, nobody is surprised.

Choosing the final number

The arithmetic gives you a range, not a target. Where you land inside it depends on the sprint:

  • Plan toward the low end when the sprint has a lot of new technology, a production release, unclear stories or a new team member who will need support.
  • Plan near the average when the work is familiar and the stories are well refined. The Definition of Ready helps you judge this.
  • Avoid planning above the top of the range. Previous high sprints usually had something favourable that will not repeat on demand.

Remember that in Scrum the Developers select how much work they take into the sprint. Velocity informs that choice; it does not replace it. If the team looks at a 19 point plan and feels it is too much, that judgement matters more than the formula.

Forecasting beyond one sprint

The same numbers answer the stakeholder question "when will it be ready?". If a release holds 120 points of estimated stories and the team finishes 19 to 27 per sprint, the release takes about 5 to 7 sprints. Quote the range, not a single date. The velocity forecast calculator produces this kind of range from your recent sprints.

Update the forecast every sprint. As stories are split and estimated, and as velocity settles, the range narrows on its own.

Common mistakes

  • Setting a velocity target. Asking the team to reach 30 points next sprint leads to bigger estimates, not more output.
  • Counting partly done work. Giving half the points for a half-finished story inflates velocity and hides carry-over.
  • Ignoring known absences. Planning a full sprint's worth of points during a holiday period guarantees a missed goal.
  • Copying another team's number. Their scale is not yours, so their total cannot tell you anything about your sprint.
  • Re-estimating to hit the number. Changing a story from 5 to 3 so it fits the sprint changes the label, not the work.

Frequently asked questions

How many story points should a 2 week sprint have?

There is no standard number. Plan around your team's average velocity from the last three to five two-week sprints, adjusted for holidays and other changes in capacity.

How many story points per developer per sprint?

Story points are a team measure, so a per-developer figure is not meaningful and tends to inflate estimates. Plan at team level using velocity and total available days.

What is a good velocity for a Scrum team?

A good velocity is a stable one. The absolute number depends on the team's own scale, so it cannot be compared with other teams. A predictable range is more useful than a high total.

How do I plan story points for a new team?

For the first sprint, let the Developers select the stories they believe they can finish, then measure what was completed. After about three sprints the team has a velocity it can use.