An estimation anti-pattern is a recurring habit in agile estimation that looks reasonable but makes estimates less useful and discussions less honest. The most common ones in planning poker are anchoring on the first number spoken, estimating in hours while calling them points, averaging votes instead of discussing them, letting a manager vote, comparing velocity between teams and estimating stories that are not ready. Each one is easy to spot once you know its shape, and most can be fixed in a single session.
Anchoring on the first number
Anchoring happens when one estimate, heard before people have formed their own, pulls everyone else towards it. In planning poker it usually sounds like this: the product owner reads the story and adds "this should be quick, maybe a 2". Or the tech lead thinks out loud before the vote. After that, the votes cluster around 2 even when the work is bigger.
A worked example. A team estimates "Add two-factor authentication by SMS". The product owner says it is "mostly configuration". Votes come in at 3, 3, 3 and 5. A month later the story has taken most of a sprint because SMS delivery needed a new provider, rate limiting and a fallback flow. The one developer who voted 5 had doubts but did not want to argue against a room that agreed.
How to fix it:
- Nobody says a number before the reveal, including the product owner and the facilitator.
- Keep votes hidden until everyone has voted, then reveal all cards at once.
- Ask people to describe the work ("what has to change?") instead of its size before voting.
Estimating in hours in disguise
This is one of the most common anti-patterns. The team uses story points on paper, but everyone silently converts: "a 1 is half a day, a 3 is a day and a half". You hear it in the conversation: "that's about two days, so a 5".
The problem is that points stop being relative. The team is back to predicting durations, which is the thing relative estimation was meant to avoid, and the estimates now depend on who picks up the story. The fixed conversion also hides uncertainty: a 13 becomes "six and a half days" and sounds precise.
How to fix it: estimate against reference stories, not against the calendar. "Is this bigger or smaller than the CSV export we did?" is a relative question. "How many days?" is not. The guide to relative estimation explains how to set up reference stories.
Averaging votes instead of discussing them
When cards are revealed, it is tempting to take the average and move on. A spread of 2, 3, 3 and 13 averages to 5.25, which rounds to 5. Nobody agreed to 5, and the person who voted 13 probably knows something the others do not.
| Votes | Average | What the spread is telling you |
|---|---|---|
| 3, 3, 3, 5 | 3.5 | Near agreement. A short check, then accept. |
| 2, 3, 5, 8 | 4.5 | Different understanding of scope. Talk before re-voting. |
| 2, 3, 3, 13 | 5.25 | Someone sees a risk the others missed. Hear the 13 first. |
| 1, 13, 2, 21 | 9.25 | The story is unclear or too big. Clarify or split. |
How to fix it: treat the spread as the output of the first round. Ask the lowest and highest voters to explain, then vote again. Use the average only as a hint when votes are already close.
The manager who votes
When a line manager or a senior stakeholder votes alongside the Developers, two things happen. People adjust their votes to match the person with authority, and the estimate stops belonging to the people who will do the work.
A related version is the manager who does not vote but overrules: "13 seems high, let's call it an 8". The 8 goes into the plan, the work still takes what it takes, and next sprint the team pads every estimate to protect itself.
How to fix it: the people who do the work vote. The product owner usually explains the story and answers questions rather than voting. Others can watch as spectators. If someone outside the team thinks an estimate is too high, the right response is a conversation about scope, which may lead to splitting the story, not a negotiation about the number.
Comparing velocity between teams
Velocity is the number of points a team completes per sprint. Because each team has its own reference stories, a point in one team is not the same size as a point in another. Team A finishing 40 points and Team B finishing 25 says nothing about which team delivers more.
Once velocity is compared or used as a performance target, teams respond in a predictable way: estimates grow. The same work that was a 3 becomes a 5. Velocity rises, nothing else changes, and the number loses its only real use, which is helping that one team forecast.
How to fix it: keep velocity inside the team as a planning tool. If leadership needs cross-team information, use outcomes such as features released, or flow measures such as cycle time.
Estimating stories that are not ready
A story arrives with a one-line title and no acceptance criteria. The team argues for ten minutes, half the conversation is about what the story should do, and the final vote is a guess. This often shows up as many "?" cards or a very wide spread.
How to fix it: agree on a lightweight definition of ready and send unclear stories back to refinement. A story is usually ready to estimate when its purpose is clear, it has acceptance criteria, and the team understands its dependencies. Estimating it later is faster than estimating it twice.
Other anti-patterns to watch for
- Re-estimating finished work. Changing an estimate after the work is done to match the actual effort hides what the team learned and makes velocity unreliable.
- Endless debate. Three rounds without agreement is a signal to split the story or take the higher value, not to keep talking.
- Giving points for bugs differently every sprint. Pick a rule for bugs and stick with it, so velocity stays comparable over time.
- Estimating only the coding. Size includes testing, review and anything else in the definition of done.
- Treating estimates as commitments. An estimate is a forecast. Holding people to it as a promise invites padding.
A quick health check
Run through this list after your next estimation session:
- Nobody said a number before the reveal.
- Nobody converted points to hours or days out loud.
- Every wide spread was discussed before the re-vote.
- Only the people doing the work voted.
- No story was estimated without acceptance criteria.
- Velocity was not compared with another team.
If two or more items fail, pick one to fix next sprint. Changing one habit at a time works better than rewriting the whole process. For a broader view of how planning poker should run, see the complete planning poker guide.
Frequently asked questions
What is anchoring in planning poker?
Anchoring is when an estimate spoken before the vote pulls everyone else towards it. Planning poker avoids it by keeping votes hidden until all cards are revealed at the same time.
Should you average planning poker votes?
Not as a rule. A wide spread means people understand the story differently. Discuss the lowest and highest votes and vote again; use the average only as a hint when votes are already close.
Can you compare velocity between two teams?
No. Each team sizes work against its own reference stories, so a point means something different in each team. Comparing velocity usually leads to inflated estimates.
Should managers vote in planning poker?
No. The people who will do the work estimate it. Managers and stakeholders can watch and answer questions, but their votes tend to pull the team towards their number.
Is it wrong to convert story points to hours?
A fixed conversion turns points back into time estimates and removes the benefit of relative sizing. Forecast with velocity measured over several sprints instead.