Sprint backlog

The sprint backlog is the plan for one sprint, made of the Sprint Goal, the product backlog items selected for the sprint and a plan for delivering them.

The sprint backlog is created during Sprint Planning and belongs to the Developers. It answers three questions: why the sprint is valuable (the Sprint Goal), what will be delivered (the selected items) and how the work will get done (the plan, often a list of tasks). It is updated throughout the sprint as the team learns more, and it should be visible enough that anyone can see the progress.

Example

For the Sprint Goal "Customers can pay by card", the sprint backlog holds five stories totalling 31 points, such as "Pay by card when the payment succeeds" and "Show a clear message when the card is declined". Under each story the Developers add tasks like "Set up payment provider test account" and "Write integration tests".

Common misunderstanding

The sprint backlog is not frozen at the end of planning. The Developers can add, remove or change tasks at any time, and they can renegotiate scope with the Product Owner as long as the Sprint Goal is kept. It is also not a list assigned person by person at the start; work is usually picked up as people become free.

Why it matters for estimation

The amount of work selected should match the team's capacity and recent velocity. See sprint capacity planning and the sprint planning guide.