Wideband Delphi estimation and how planning poker derives from it

Wideband Delphi is a structured way for a group of experts to reach an estimate through rounds of anonymous estimates and open discussion. This guide explains the method, where it came from and how planning poker simplified it.

On this page
  1. From Delphi to Wideband Delphi
  2. How Wideband Delphi works
  3. A worked example
  4. How planning poker derives from Wideband Delphi
  5. Why independent estimates matter
  6. When Wideband Delphi still fits
  7. Lessons to carry into planning poker
  8. Frequently asked questions

Wideband Delphi is a consensus-based estimation technique in which a group of experts estimate the same work independently and anonymously, discuss the differences between their estimates, and repeat until the estimates converge. It was developed by Barry Boehm and John Farquhar at the RAND Corporation in the 1970s as a variant of the earlier Delphi method, and it is the direct ancestor of planning poker.

The idea at its core is simple: get independent opinions first, so nobody is anchored, then use discussion to share what each person knows.

From Delphi to Wideband Delphi

The original Delphi method was also developed at RAND, as a way to forecast with a panel of experts. Each expert answered a questionnaire anonymously, a coordinator summarised the answers and sent the summary back, and the experts revised their answers. The experts did not talk to each other. Anonymity kept strong personalities from dominating, but it also meant people could not explain their reasoning.

Boehm and Farquhar found that for software estimation, this lack of communication was a problem. Estimates differ mostly because people assume different things about the work. A summary of numbers does not reveal those assumptions. So they added group discussion between rounds while keeping the estimates themselves anonymous. "Wideband" refers to this wider channel of communication between the estimators.

AspectDelphiWideband Delphi
EstimatesAnonymousAnonymous
Discussion between roundsNone, only a written summaryGroup discussion of the differences
Role of the coordinatorCollects and summarises answersCollects, summarises and leads the discussion
Typical useForecasting, policy questionsSoftware size and effort estimation

How Wideband Delphi works

Descriptions vary slightly, but a Wideband Delphi session generally follows these steps:

  1. Kickoff. A coordinator gives each estimator the specification and an estimation form. The group meets to discuss the work, its scope and the assumptions they will use. Nobody gives a number yet.
  2. Individual estimates. Each estimator works alone, breaks the work down into tasks, and writes down an estimate, along with the assumptions behind it.
  3. Summary. The coordinator collects the forms and prepares an anonymous summary: the range of estimates, and often the main assumptions.
  4. Discussion. The group meets again and discusses the points where estimates differ most. Nobody has to defend their own number, because the numbers are anonymous.
  5. Re-estimate. Each estimator revises their estimate, again alone and anonymously.
  6. Repeat. Rounds continue until the estimates fall within an acceptable range, or a set number of rounds has passed. The coordinator then records the final figure and the agreed assumptions.

A worked example

A team of five is asked how long it will take to add a payments module to an internal ordering system. The coordinator runs Wideband Delphi in person-weeks.

  • Round 1: estimates of 4, 5, 6, 9 and 14 person-weeks. The spread is wide.
  • Discussion: the person who estimated 14 assumed refunds and partial payments were in scope. The person who estimated 4 assumed a hosted payment page with no stored card data. The group checks the specification and agrees that refunds are in scope and partial payments are not.
  • Round 2: estimates of 7, 7, 8, 9 and 10 person-weeks. The spread is now narrow enough.
  • Result: the coordinator records 8 person-weeks, with a range of 7 to 10, and lists the assumption about refunds and partial payments.

The number moved, but the most valuable output was the list of assumptions. Without the discussion, the 4 and the 14 would have been averaged and the disagreement about refunds would have surfaced months later.

How planning poker derives from Wideband Delphi

James Grenning described planning poker in 2002, and Mike Cohn later popularised it. It keeps the core loop of Wideband Delphi (independent estimate, discussion, re-estimate) and removes most of the ceremony.

Wideband DelphiPlanning poker
Anonymous written estimatesHidden cards revealed at the same time
Coordinator summarises between roundsEveryone sees all cards immediately
Separate meetings for each roundRounds of one or two minutes in a single session
Estimates in time, such as person-weeksUsually relative sizes, such as story points
Detailed task breakdown by each estimatorQuick comparison with reference stories

The biggest change is that planning poker gives up full anonymity. Cards are revealed together, so nobody is anchored, but people can see who voted what. In exchange, the lowest and highest voters can explain their reasoning straight away, which is what makes a round so fast. The second change is the move to relative estimation, which removes the need for a detailed task breakdown before each estimate.

Why independent estimates matter

Both methods rest on the same observation: the first number spoken in a group pulls the others towards it. This effect is called anchoring, and it works even when people know about it. A senior developer who says "probably two weeks" before anyone else has thought about the work has, in effect, set the estimate for the room.

Independent estimates protect against anchoring in two ways. First, every estimator has to think about the work on their own, which brings out more assumptions. Second, the spread of estimates becomes visible. A narrow spread means the group shares an understanding of the work. A wide spread means it does not, and that is exactly the information a planning meeting needs.

Groups that skip this step often reach agreement quickly and are wrong together. The estimation anti-patterns guide covers anchoring and other habits that undo independent estimates, and the overview of agile estimation techniques shows where Delphi-style methods sit among the alternatives.

The estimate that differs most from the rest is not a problem to correct. It is the most useful input in the round, because it usually comes from someone who knows something the group has not discussed yet.

When Wideband Delphi still fits

In agile teams planning poker is now far more common than Wideband Delphi, but the original still has a place:

  • Large, one-off estimates such as a bid or a project budget, where you want written assumptions and a documented range.
  • Groups with strong hierarchy, where full anonymity helps people say what they actually think.
  • Experts who cannot meet often, since rounds can run asynchronously over a few days.

Lessons to carry into planning poker

  • Independent estimates first. Keep votes hidden until everyone has chosen. This is the rule planning poker inherited from Delphi.
  • Discuss assumptions, not numbers. Ask "what did you assume?" rather than "why did you vote 13?".
  • Write down what you agreed. A short note on the story about scope decisions saves the same discussion next time.
  • Limit the rounds. Wideband Delphi sets a maximum number of rounds. In planning poker, two or three rounds is usually enough before splitting the story or taking the higher value.

Frequently asked questions

What is Wideband Delphi?

Wideband Delphi is a group estimation technique where experts estimate independently and anonymously, discuss the differences, and re-estimate until the estimates converge.

Who created Wideband Delphi?

Barry Boehm and John Farquhar developed Wideband Delphi at the RAND Corporation in the 1970s, as a variant of the earlier Delphi method also developed at RAND.

What does wideband mean in Wideband Delphi?

It refers to the wider communication between estimators. Unlike the original Delphi method, estimators discuss their differences as a group between rounds.

How is planning poker related to Wideband Delphi?

Planning poker is a lightweight form of Wideband Delphi. It keeps independent estimates followed by discussion and re-estimation, but uses hidden cards revealed together and short rounds in a single session.