Planning poker across time zones works best as a short live session inside the hours when everyone is online, supported by preparation that happens asynchronously. The team reads the stories and posts questions in advance, the Product Owner answers them before the session, and the live part is kept to voting, revealing and discussing the stories where votes differ. Done this way, a distributed team can estimate ten stories in thirty to forty minutes.
Remote planning poker on its own is mainly a tooling question. Distributed teams have a harder constraint: the overlap between working hours may be two hours a day or less, and every meeting competes for it. This guide focuses on that constraint. For the basics of running estimation over video, see remote planning poker.
Why the vote itself stays live
It is tempting to make estimation fully asynchronous: everyone votes when it suits them, and the numbers are averaged. That loses most of what makes planning poker useful. The value lies in revealing votes at the same moment and talking about the differences straight away. A 2 and a 13 on the same story are a prompt for a conversation, not two numbers to average to 7.5.
Scrum Poker sessions are live: participants join the same session and votes are revealed together. That suits the approach in this guide, where asynchronous work goes into preparation and the voting happens in a short shared window.
Finding the overlap
Start by mapping working hours. A simple table makes the window obvious and stops people from assuming that "the morning" means the same thing for everyone.
| Location | Working hours (local) | Same window in UTC |
|---|---|---|
| Lisbon | 09:00 to 17:30 | 09:00 to 17:30 (winter) |
| Warsaw | 09:00 to 17:00 | 08:00 to 16:00 (winter) |
| Pune | 11:00 to 19:30 | 05:30 to 14:00 |
| Toronto | 08:30 to 17:00 | 13:30 to 22:00 (winter) |
In this example everyone is online between 13:30 and 14:00 UTC, a thirty-minute window. Pune is at the end of its day, Toronto at the start. Thirty minutes is enough for a well-prepared session, but only if the preparation is done.
Daylight saving time changes on different dates in different countries, and some places do not observe it at all. Check the overlap again around those dates, because a window can shrink or vanish for a few weeks.
Prepare stories in advance
Preparation is what makes a short session possible. Aim to finish it a full working day before the live vote, so that every location has had a chance to read and respond.
- The Product Owner publishes the list. Eight to twelve stories, each with a title, a short description and acceptance criteria. Use the same written format every time.
- Everyone reads and comments. Each Developer reads the stories during their own working day and posts questions in the shared backlog or the team chat, next to the story they concern.
- The Product Owner answers. Answers go in the same thread, so the next time zone sees them on waking up.
- Stories that are not ready drop out. If a question cannot be answered in time, the story waits for the next session rather than taking up live time.
- The facilitator sets the agenda. The final list, in order, goes into the session before it starts.
This is ordinary backlog refinement, done in writing. Teams that already use a refinement checklist can use it as the standard for what "ready to vote" means.
The async pre-read, then a short live vote
Here is the pattern in practice for the team in the table above, estimating on a Thursday.
- Tuesday, Lisbon morning: the Product Owner posts ten stories with acceptance criteria.
- Tuesday, across the day: Pune and Warsaw read and post questions; Toronto reads at the end of its day and adds two more.
- Wednesday: the Product Owner answers every question. One story about tax rules depends on an answer from finance, so it is moved to next week.
- Thursday, 13:30 UTC: the live session. The facilitator skips reading stories aloud and opens the first vote straight away. Most stories take about two minutes. Two stories with split votes take about six minutes each.
- Thursday, 14:00 UTC: nine stories estimated. Results are shared in the team chat for anyone who could not attend.
Notice that the session started with a vote, not with a presentation. Everyone had read the stories, so the facilitator only named each one, confirmed there were no new questions, and opened the round. If someone had not done the pre-read, the facilitator moved on anyway; the team agreed beforehand that the written thread is the place to catch up, not the live window.
The live time drops because the questions that usually fill the first minutes of each story were already answered in writing. What remains is the part that needs everyone at once: secret voting, a shared reveal and the discussion of outliers.
Running the live session
- Start on time, exactly. In a thirty-minute window, a five-minute late start costs a sixth of the session.
- Join on any device. People at the edge of their day may join from a phone. In Scrum Poker, phones join by QR code or link, with no sign-up.
- Use a voting timer. It keeps each round moving and avoids waiting on one person.
- Keep explanations short. One minute for the lowest and highest voters, then revote.
- Park quickly. If a story is still split after two rounds, move it to the written thread and continue.
- Record and share. Post the agreed values where the whole team can see them, including people who missed the session.
When there is no overlap at all
Some teams have no shared working hours. That is a structural problem, and estimation is only one of the places it shows. Options include:
- An occasional session outside normal hours for one group, rotated fairly and kept short.
- Splitting into two teams with separate backlogs, each with its own overlap.
- Estimating in two regional sessions and reconciling differences in writing, accepting that this is slower and loses some of the shared conversation.
- Coarser sizing, such as T-shirt sizes, that needs less discussion per item.
Checklist for distributed estimation
- Overlap window mapped and rechecked around daylight saving changes.
- Stories published at least one working day before the session.
- Questions and answers kept in writing, next to each story.
- Stories with unanswered questions removed from the agenda.
- Session starts on time, with the agenda already loaded.
- Results shared in writing straight after the session.
- Session time rotated if the overlap falls at the edge of someone's day.
Review the setup at a retrospective every few months. Time zones, holidays and team membership change, and a session time that suited everyone in spring may not suit them in autumn.
Frequently asked questions
How do you run planning poker across time zones?
Prepare stories asynchronously at least a day in advance, collect and answer questions in writing, then run a short live voting session inside the hours when everyone is online.
Can planning poker be done asynchronously?
Preparation can be asynchronous, but the vote works best live, because revealing votes together and discussing differences straight away is where most of the value comes from.
How long should a distributed planning poker session be?
With good preparation, about thirty to forty minutes for eight to twelve stories. Most of the time saved comes from answering questions in writing before the session.
What if a distributed team has no overlapping hours?
Options include rotating an occasional out-of-hours session, splitting into regional teams, or estimating in two regional groups and reconciling in writing. Each has trade-offs.